NRC Moves Forward on Exelon ESP Application

Last week, the NRC announced its preliminary conclusion that they have found no environmental impacts that would prevent approval of Exelon’s Early Site Permit (ESP) application for the Clinton plant in Illinois. This article appeared in the St. Louis Post-Dispatch last week.

The article highlights an important point:
Besides environmental effects, the commission also is considering site safety and emergency planning. The commission has said it wants to make a decision on Exelon's application by August next year.
The myriad of other issues associated with licensing a new nuclear plant are addressed during other steps of the process like the certification of plant design and the application for a combined construction and operating license.

This is a concept that, in my experience, many antinuclear extremists can’t seem to grasp. They will allege that an ESP application is incomplete because it doesn’t say enough about specific safety features of the plant design or it doesn’t address storage or disposal of spent fuel.

Occasionally, when this feature of the licensing process is pointed out, a better-versed antinuclear leader will say, “Yes, and that is a fundamental flaw in the regulations. All of these issues should be addressed together.” I find this logic ludicrous. How does one provide sufficiently detailed analyses of safety systems when a design hasn’t been chosen? And how can one provide specifics of spent fuel storage and disposal when the parameters of the fuel are not yet known? Any such analyses at the ESP stage would be speculative at best and would not serve well the interests of the NRC, the utility, or the public.

Comments

Norris McDonald said…
Great new about Exelon. Now if they could get new plant on line in seven years I would really be impressed. Does Exelon really understand how important speed is here? And this assumes that they have excellent quality control.
Lisa Stiles said…
I think that all the utilities that are pursuing ESPs are aware of the importance of showing investors that plants can be built on schedule.

I'm not in a position to know exact timeframes but the information I've gleaned at conferences and the like is that utilities and vendors would want to be sure they can have a new plant on line 4 years from the time the order is placed.

Of course, orders won't be placed until and if licensing and economic issues are resolved favorably. Given the length of time for the different steps in the licensing process, I doubt seriously that we will see a new nuclear plant online by the 2010 DOE target. But if everything comes together, I don't think it is unrealistic to expect a new one before 2015.

Popular posts from this blog

An Ohio School Board Is Working to Save Nuclear Plants

Ohio faces a decision soon about its two nuclear reactors, Davis-Besse and Perry, and on Wednesday, neighbors of one of those plants issued a cry for help. The reactors’ problem is that the price of electricity they sell on the high-voltage grid is depressed, mostly because of a surplus of natural gas. And the reactors do not get any revenue for the other benefits they provide. Some of those benefits are regional – emissions-free electricity, reliability with months of fuel on-site, and diversity in case of problems or price spikes with gas or coal, state and federal payroll taxes, and national economic stimulus as the plants buy fuel, supplies and services. Some of the benefits are highly localized, including employment and property taxes. One locality is already feeling the pinch: Oak Harbor on Lake Erie, home to Davis-Besse. The town has a middle school in a building that is 106 years old, and an elementary school from the 1950s, and on May 2 was scheduled to have a referendu

Why Ex-Im Bank Board Nominations Will Turn the Page on a Dysfunctional Chapter in Washington

In our present era of political discord, could Washington agree to support an agency that creates thousands of American jobs by enabling U.S. companies of all sizes to compete in foreign markets? What if that agency generated nearly billions of dollars more in revenue than the cost of its operations and returned that money – $7 billion over the past two decades – to U.S. taxpayers? In fact, that agency, the Export-Import Bank of the United States (Ex-Im Bank), was reauthorized by a large majority of Congress in 2015. To be sure, the matter was not without controversy. A bipartisan House coalition resorted to a rarely-used parliamentary maneuver in order to force a vote. But when Congress voted, Ex-Im Bank won a supermajority in the House and a large majority in the Senate. For almost two years, however, Ex-Im Bank has been unable to function fully because a single Senate committee chairman prevented the confirmation of nominees to its Board of Directors. Without a quorum

NEI Praises Connecticut Action in Support of Nuclear Energy

Earlier this week, Connecticut Gov. Dannel P. Malloy signed SB-1501 into law, legislation that puts nuclear energy on an equal footing with other non-emitting sources of energy in the state’s electricity marketplace. “Gov. Malloy and the state legislature deserve praise for their decision to support Dominion’s Millstone Power Station and the 1,500 Connecticut residents who work there," said NEI President and CEO Maria Korsnick. "By opening the door to Millstone having equal access to auctions open to other non-emitting sources of electricity, the state will help preserve $1.5 billion in economic activity, grid resiliency and reliability, and clean air that all residents of the state can enjoy," Korsnick said. Millstone Power Station Korsnick continued, "Connecticut is the third state to re-balance its electricity marketplace, joining New York and Illinois, which took their own legislative paths to preserving nuclear power plants in 2016. Now attention should